Grumman Aircraft Engineering Corporation

LOG


Page No 73117

Engineer

DOWSE/SARBELLO

Project

LM-5

Location

ACE 3

Time

DAY SHIFT

Title

Date

8/19/68

1. COMPLETED SEQ 077 (X-LUNAR BUS ISOLATION TEST) LESS RREA & RRAS. ISOLATION TEST TO BE REPERFORMED AT A LATER DATE WHEN ABOVE MENTIONED UNITS ARE INSTALLED. TDR #33 TO REMAIN OPEN TILL THEN.

2. PREPARATION WITH DEPT'S 053 & 063 IN WORK IN RELATION TO REASSEMBLING ECA #4 HARDWARE. TDR #3 TO BE USED TO REASSEMBLE, TORQUE AND BIDDLE-DUCTER TESTING.

3. AFTER ACTIVATION OF THE CIRCUIT MONITOR MODULES THE SYS A CABLE CUTTER T (RED) LIGHT CAME ON (3A5A2)

RESET AT 232 : 19.37.01 BY INSERTING IN R-START 080
0001 XEQ & VERIFIED
0000 XEQ & VERIFIED


4. RAN SEQUENCES #233 THRU #238 ON TDR #3 AFTER ECA 4-4, 4-2 & 4-1 TERMINALS WERE CLEANED OF POTTING MATERIAL & DEGREASED. BIDDLE-DUCTER RETEST WAS VERY FAVORABLE. FINAL RESULTS TO BE EVALUATED DURING RERUN OF SEQUENCES RELATED TO TDR #3, #4, #5 & #6.



Engineer

A. Hecht

Project

Location

Time

Night Shift

Title

Date

8/19/68 to 8/20/68

1. 2304: Observed SYS A CABLE CUTTER T (RED) ED LT on 3A5A2 was ON. Reset as above, except 2nd step was 0000 XEQ & verified.

2. 0145: Same observation & action as item #1.

3. G & N running a T/S all night. No EPS activity on vehicle.

4. Note to Day Crew: Dev #137 thru 145, written 8/10, are still in black notebook. They require sig & incorporation into OCP.