Grumman Aircraft Engineering Corporation

LOG

Page No 73113

Engineer

E. Homburger / A. Hecht

Project

LM-5

Location

HCE 3

Time

Day Shift

Title

-

Date

8-14-68

(1) Attempted to T/S TDR #3 further. Got shut off because G & N are running. Standing by for G & N completion.

(2) Completed TDR #3 continuation sheets 39 thru 42.



Engineer

S. SARBELLO

Project

Location

Time

NIGHT SHIFT

Title

Date

8/14-15/68


1. COMPLETED RERUN SEQ 065 (FLOOD LTG) VIA DEVIATION #147. TEST CHECKOUT GOOD.

2. RAN CONFIDENCE CHECK ON DOCKING (SEQ 076) & NUMERICS (SEQ 073) VIA TDR #32 WITH LCA P1/J1 MATED. AC & DC OUTPUTS OK. TDR #32 TO BE SOLD TODAY 8/15/68 BY BILL SEID. ALL TESTS CHECK GOOD.

3. WROTE & RAN DR #13 SEQ'S #243L THROUGH #243X CHECKING OUT MASTER ALARM INHIBIT CIRCUIT RESPONSES TO PANEL #14 INVERTER SWITCH FUNCTIONS. ALL TESTS CHECKED GOOD -- NO MATER ALARM ACTIVATIONS.

4. LEFT GSE AC PWR OFF VEHICLE AND POWERED DOWN D.C. 82090 POWER SUPPLIES. POWERED UP VIA 82140 TO CONFIGURE VEHICLE & GSE FOR STARTING SEQ 77 (X-LUNAR BUS ISOLATION CHECK). CONFIGURED VIA DEVIATION #69, 62000-CON-LM5.

5. RECEIVED TDR #33 AT SEQ 077-020-03.

6. 0600 -- STARTED TROUBLESHOOTING TDR #33.

7. GET DEVIATION #148 SIGNED OFF BY RASPO.