Grumman Aircraft Engineering Corporation

LOG

Page No 73110

Engineer

S. SARBELLO

Project

LM-5

Location

PLT 5

Time

DAY SHIFT

Title

Date

8/10/68

1. ASSIGNED STE DUTY FOR ACE 3 STATION FOR TODAY. NO TURNOVER REQUIRED FOR TONIGHT. NO COVERAGE OR SUPPORT REQUIRED FOR BOTH SHIFTS ON 8/11/68.

2. WROTE POST TEST DEVIATIONS #137 THRU #145 (STANDARDIZATION OF SEQ'S #055 THRU #058, BAT 1 THRU BAT 4 REVERSE CURRENT TESTS).

3. NASA'S JOHN HAWK TOO BUSY TO SIGN DOCUMENTS SO HAVE TOM MARTIN SIGN THEM MONDAY.

4. TDR #31 CONTINUATION SHEETS HAVE LOCATED INTEGRAL LIGHTING SHORT IN PANEL #2'S P804, PINS #1 & #2 (1/2 INCH FROM CONNECTOR - SHORT LOCATED BY REFLECTOMETER).

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Engineer

E. HOMBURGER / A. HECHT

Project

Location

Time

DAY SHIFT

Title

Date

8/12/68

1. Ran TDR 3 shts 29 thru 36 (Line drop data)

2. TDR #3 still requires:

c. P/J 105 Bob removal & Conn remate
d. P/J 87 Bob removal & Conn remate
a. On pnl 16, pull "HTRS, RCS Sys A/B, Quad 2".
pull "ASC ECA CONT CB
b. On pnl 11, pull "DES ECA CB".

3.Nonpwrd via bat 5 NF.